Hearing Technology Limited approached AP Design to convert a recently purchased house into a new hearing centre complete with sound proof room.

The project commenced and AP Design was engaged for contract management. Halfway through the project the client informed the construction team that their lease was terminated and the project needed to be completed in 4 weeks, reducing the programme by 3 weeks. The builder worked extra hours and completed the project allowing the centre to open.

The sound proof room which is 100% isolated from the rest of the house including the foundation works perfectly even though it is next to the busy Marshlands road.